考试首页 | 考试用书 | 培训课程 | 模拟考场 | 考试论坛  
  当前位置:考试网 >> ACCA/CAT >> 备考指导 >> 文章内容
  

ACCAP5辅导:SoftwareSupplierSelection

考试网  [ 2017年5月2日 ] 【

  小编为大家整理了ACCA P5知识点:Software Supplier Selection的辅导讲义。

  1. Software Supplier Selection

  Ideally, this process will revolve around the Invitation to Tender (ITT), which has set out the firm's functional, technical and contractual requirements such that the project team can compare competing solutions. The ITT may also be known as a Request for Proposal (RFP).

  Skidmore and Eva suggest a five-stage process for vendor selection.

  1.1. Obtaining tenders: The ITT will typically be sent to several companies with capability to deliver the system change and will include sections that describe the response process, the response format and key dates. In addition, the ITT will have the following sections:

  Background

  Summary of current IT system(s)

  Key functional requirements

  Key technical requirements

  Price considerations

  Request for references

  1.2. First-pass selection: For common, off-the-shelf systems, there may be many vendors that can supply the software. The first pass allows the selection committee to identify three to six suppliers that specify the best software solution, implementation process and value for money.

  Generate a worksheet documenting responses to key points in the ITT.

  Sort the worksheet based on these responses.

  Screen down to a number of vendors that the committee can further explore.

  1.3. Second-pass selection: The selection committee does an indepth review of firms surviving the first pass.

  Schedule and hold supplier presentations.

  Contact references provided in the ITT process.

  For larger or more complicated projects, it may be necessary for the IT team to assess the supplier

  Determine each supplier's financial stability.

  Select two to three of the most promising suppliers.

  Conduct site visits where the software has been implemented.

  Decide on a vendor.

  1.4. Implementation: This will include all steps required to

  realise the key success criteria:

  equipment installation (if necessary);

  software installation and time frames;

  software customisation and response times; and

  training.

  1.5. Managing the long-term relationship: This part of the selection process should be specified to some extent during the second-pass selection stage, and finalised prior to actually negotiating and signing the final contract. This will involve the steps in virtually any relationship, including:

  developing (and limiting) expectations on both sides;

  establishing channels of communication; and

  establishing key dates and reminding the supplier of key dates at various points through implementation, update, upgrade and all other points in the cycle.

本文纠错】【告诉好友】【打印此文】【返回顶部
将考试网添加到收藏夹 | 每次上网自动访问考试网 | 复制本页地址,传给QQ/MSN上的好友 | 申请链接 | 意见留言 TOP
关于本站  网站声明  广告服务  联系方式  站内导航  考试论坛
Copyright © 2006-2019 考试网(Examw.com) All Rights Reserved  营业执照