考试首页 | 考试用书 | 培训课程 | 模拟考场 | 考试论坛  
  当前位置:考试网 >> ACCA/CAT >> 备考指导 >> 文章内容
  

2016年ACCA考试《F9财务管理》辅导资料(11)_第2页

考试网  [ 2016年7月20日 ] 【

  1 + m =(1 + r) x (1 + i)

  Where:

  m = money rate

  r = real rate

  i = inflation rate

  From the above formula it is possible to calculate m, r and i if you were given information about two of the three variables. For example if you were told that the money rate was 20% and real rate was 12% the inflation rate will be calculated as follows:

  i =1 + m ? 1

  1 + r

  i =1 + 0.20? 1

  1 + 0.12

  i =1.0714?

  = 7.14%

  Equally m and r could be calculated as follows.

  m =(1.12 x 1.0714) ? 1

  (1.19999) ? 1

  20%

  r =1.20? 1

  1.0714

  12%

  When the appropriate discount rate has been established the present value factors of this rate at different time periods can be obtained from the present value table or the present value factors calculated using the following formula:

  11111

  (1+r)(1+r)2(1+r)3(1+r)4(1+r)5?etc

  Where r = discount rate.

  Present value tables are only available for whole numbers, so if your r is not a whole number you will have to use the formula to calculate the required present value factors. Let us calculate for example the present value factors of 7.14% for years 1 to 5.

  11111

  (1.0714)(1.0714) 2(1.0714) 3(1.0714) 4(1.0714)5?etc

  0.9330.8710.8130.7590.708

  Having either obtained or calculated the present value factors for the relevant discount rates, these are then used to discount the future cash flows to give the net present values of the projects. It is important to understand when to use which rate. If the question gives you money cash flows, then use the money rate; if the question gives real cash flow it follows then that the real rate must be used. To confuse one with the other would give the wrong answer.

  12%

  When the appropriate discount rate has been established the present value factors of this rate at different time periods can be obtained from the present value table or the present value factors calculated using the following formula:

  11111

  (1+r)(1+r)2(1+r)3(1+r)4(1+r)5?etc

  Where r = discount rate.

  Present value tables are only available for whole numbers, so if your r is not a whole number you will have to use the formula to calculate the required present value factors. Let us calculate for example the present value factors of 7.14% for years 1 to 5.

  11111

  (1.0714)(1.0714) 2(1.0714) 3(1.0714) 4(1.0714)5?etc

  0.9330.8710.8130.7590.708

  Having either obtained or calculated the present value factors for the relevant discount rates, these are then used to discount the future cash flows to give the net present values of the projects. It is important to understand when to use which rate. If the question gives you money cash flows, then use the money rate; if the question gives real cash flow it follows then that the real rate must be used. To confuse one with the other would give the wrong answer.

1 2
本文纠错】【告诉好友】【打印此文】【返回顶部
将考试网添加到收藏夹 | 每次上网自动访问考试网 | 复制本页地址,传给QQ/MSN上的好友 | 申请链接 | 意见留言 TOP
关于本站  网站声明  广告服务  联系方式  站内导航  考试论坛
Copyright © 2006-2019 考试网(Examw.com) All Rights Reserved  营业执照